The project has been reworked based on citizen feedback gathered during the presentation of the preliminary draft. Adaptations include a redesign of the playground areas to avoid conflicts with cyclists, an increase in the number of planned trees, and the replacement of deactivated concrete surfacing with stabilized dolomite on the main paths, while ensuring PMR access to the playground.
The submitted permit file is accessible online on the City's website. The public inquiry runs from Friday, November 20 to Monday, December 21, 2026, at 11 a.m.
The permit could be issued in the summer of 2027, after which the City will initiate the necessary administrative procedures to launch the works contracts. A participatory workshop will soon be organized to establish the specifications for the playground.
This project benefits from 80% funding from the Walloon Region as part of the Integrated City Policy (P.I.V), with the remaining balance to be borne by the City of Tournai.