The renovation works in the heart of Celles are progressing, with key stages planned until the second quarter of 2027. Rue Ducellier is seeing the continuation of paving stone installation in November 2026, followed by the application of deactivated concrete in December 2026 - January 2027. The road is expected to reopen at that time.
In December 2026 - January 2027, Rue de l’Église is scheduled to have its asphalt surface laid, pending necessary checks of the sewage system. Between January and February 2027, work will primarily focus on the south side of the church, with the possibility of alternating traffic on Rue de l’Église.
March and April 2027 will involve finishing touches to the presbytery park and landscaping of the parvis. These interventions may lead to temporary closures of Rue de l’Église, with diversions in place. Access to shops on Rue Leclercqz will be maintained via Rue Parfait, which will be temporarily organized as a two-way street with traffic lights.
The next phase, concerning Place Verte, is scheduled for the second quarter of 2027, with an indicative duration of approximately one year. The redevelopment of Celles' center aims to sustainably improve the quality of life and address issues of runoff and flooding.
Unforeseen technical difficulties have necessitated adjustments to the initial schedule. To minimize delays, some interventions are being carried out simultaneously. The municipality has also decided to enhance its communication efforts to keep citizens more frequently informed about the construction progress.